PSE has decided to start the Power Pole project in CVHA. The latest timetable has Potelco preparing poles for removal and installation this week, with the actual removal/installation to begin next Monday the 23rd.
The only reason water service may be interrupted is if a break occurs during this phase of the project.
Since we must have the main charged to identify any problems we will have personnel on standby in case an issue develops. If a break occurs we will coordinate with Potelco and PSE to get the water service restored as soon as possible and inform affected homeowners of an estimated restore time.
There may also be some intermittent power outages as transformers and etc. are moved from the old to the new poles, these should be of short duration.
Most of these possible outages should be limited to CV1.

GCastellane for the CVHA Board of Directors.